223(f) or 221(d)(4) for a renovation? Where the line is

A renovation stays a 223(f) deal as long as the total construction cost stays under HUD’s aggregate cost limit: $20,406 per unit in 2026, times the area’s high-cost percentage, times the number of units. Above that line the work is substantial rehabilitation, and the loan has to be a 221(d)(4).

At the 270% high-cost percentage that applies across the contiguous states in 2026, the line is about $55,100 a unit; in Alaska, Hawaii, Guam and the U.S. Virgin Islands (405%) it is about $82,600.

How HUD counts the cost

The MAP Guide (section 5.1.2) defines the aggregate cost as everything spent on construction at the property: hard costs, the general contractor’s fee and the architect’s fee, plus whatever gets spent from the contingency and completion escrows, plus change orders. For a tax credit deal HUD assumes the whole contingency is spent. And the test applies to the final number, at completion, not just the estimate at application.

So a 223(f) budget that starts at $50,000 a unit can cross the $55,100 line through change orders after closing.

A worked example

A 160-unit property in a 270% area. The line is 160 × $20,406 × 2.70, about $8.82 million.

  • Plan A: $7.2 million of work, $45,000 a unit, plus a $720,000 contingency (10%) that goes unspent. A 223(f) with repairs: no Davis-Bacon, a 35-year term, HUD’s quicker existing-property process.
  • Plan B: $9.6 million, $60,000 a unit. Substantial rehabilitation. A 221(d)(4): Davis-Bacon wages on the work, the construction-loan process, up to 40 years, and an upfront premium of 0.25% for each construction year.

If Plan A’s contingency gets spent and change orders add $900,000, the final cost is $8.82 million, which meets the line exactly. A few more dollars and it fails. Owners that close to it either cut scope or plan for 221(d)(4) from the start.

What else pushes a deal to 221(d)(4)

  • Adding units. 223(f) allows repairs, not new dwelling units (MAP Guide 3.7.5).
  • Work that needs the construction-loan structure: tenants moving out, phased gut renovation, long construction periods.

Sources

  • HUD Mortgagee Letter 2026-05 (May 20, 2026): 2026 base per dwelling unit $20,406; high-cost percentages.
  • HUD MAP Guide, 2020 edition revised March 2021, sections 3.7.5 and 5.1.2.

About the author

Janover Capital LLC, commercial mortgage team. Prepared by the commercial mortgage team at Janover Capital LLC. Sources are cited at the bottom of each page, with their dates.

Have a question?

Send it to the desk at Janover Capital LLC. A person there will reply.

Send a deal